01Which house this is about
| Item | Value |
|---|---|
| Where | Latvia, about 30 km from Riga, 200 m from a lake |
| Area | 157 m² |
| Frame | timber, assembled glued beams in the FapTech technology |
| Timber | C24, dried |
| Foundation | strip foundation, the house raised on tall supports |
| Estimated cost | about €250,000, roughly €1,600/m² (2025 prices) |
| Made by | the WWL HUS factory, Latvia |
02What the frame of such a house costs: a calculator run
Half of the mistakes below are about numbers nobody worked out in advance. So the calculation comes first. I entered a one-storey house of 8 × 15.1 m into the jem.house calculator, about 121 m² by the outer outline: a gable roof, 10 panoramic windows and a sliding door of 2 × 2.1 m. The dimensions are notional: this is not the plan of the house in the video. The price is calculated by the manufacturer, not by the site: in Latvia the timber frame on jem.house is currently priced by Zogal House, at its own rates per m² of panel.
| Item | Value |
|---|---|
| Area by the outer outline | 120.8 m² |
| Usable area | 108.2 m² |
| Frame timber volume | 9.31 m³ |
| External walls, less windows and doors | 143.2 m² |
| External wall | 280 mm, €110/m² |
| Roof trusses | €50/m² |
| Assembly | €70/m² |
| Delivery | €10/m² |
| Engineering | €8/m² |
| Frame price incl. 21 % VAT | €37,125 |
| Excl. VAT | €30,682 |
Source: the Zogal House calculator on jem.house, 2026 rates stated by the manufacturer. Calculated on 22.11.2026. Open this house in the calculator and change the dimensions.
This is the price of a conventional frame from another manufacturer, not the budget of the house in the video. It is there for scale: the frame with assembly is about €37,000, and I estimate the whole turnkey house at about €250,000. The difference is everything the frame price leaves out.
03Plot and money
1. The plot was chosen on emotion
The lake is 200 metres away, the city half an hour. In a place like that it is easy to spend any amount when you build for yourself. The question to ask before buying: what happens when the house has to be sold or let. The answer is in the next two points.
2. The building cost was not compared with rental income
I use a simple rule: a house should pay for itself in 100 monthly rents. This is my own rough check, not a standard.
For this house the calculation is:
| Step | Calculation | Result |
|---|---|---|
| Price per night at the neighbours | from a booking site | about €70 |
| A month fully booked | €70 × 30 | €2,100 |
| A year fully booked | €2,100 × 12 | €25,200 |
| At 0.6 occupancy | €25,200 × 0.6 | about €15,100 a year |
| Average per month | €15,100 / 12 | about €1,260 |
| 100 monthly rents | €1,260 × 100 | about €126,000 |
The house costs about €250,000. By this rule it is twice as expensive as the rent in this place allows.
3. Nobody looked at the neighbours
For the calculation to work, a house like this would have to rent for about €200 a night. The offers around it are €50–115. In the end the market around sets the price, not the budget. Open a booking site for your location before you order a design.
04Frame and plot
4. A complex frame was chosen where a conventional one would do
The frame of this house is built in the FapTech technology: battens are glued and screwed together into one block. Such a beam carries a large load and spans long distances. Here, for example, the veranda hangs above the ground without columns.
It looks good and it works, but it costs more than a conventional frame. For the manufacturer the house is a showcase, so for them it is justified. For a private client the question is simple: do you need those spans.
5. Nobody worked out what the slope would cost
The plot slopes steeply. So that the house would face the lake and not the beach cabins, it was raised on tall supports. The view worked out. But the supports, the floor over the open space below and the soffit underneath are extra money that a level plot does not need.
6. Upkeep of exposed timber was not budgeted
The beams were painted at the factory. Cracks appeared in them already during construction: the timber is drying, and that is normal. Over time the paint peels along the cracks.
What this means for the owner: exposed timber has to be cleaned, primed and painted again. By my estimate, two or three times in 10 years. Take this into account before leaving the frame on show.
7. Looks were chosen where metal is more practical
The supports under the house could have been made of steel, with the timber frame on top. It would have been noticeably cheaper, and they would not need painting every three years. Here timber was chosen for the look. That is a fair choice if you know its price in advance.
How a steel frame is built and how it differs from timber is in the article on light steel frame houses.
05Windows and heat
8. The glazing was not counted
The house has almost 10 panoramic windows and one sliding one, onto the veranda. A sliding unit costs about twice as much as a fixed panoramic window of the same size. The saving here was the right one: the sliding window went in only where there is a way out.
The entrance door is glass, with triple glazing and an extra pane of toughened glass outside. It is warm and expensive. In a house like this the glazing is one of the largest items in the budget, so count it as a separate line.
9. Energy efficiency was expected from insulation thickness alone
The design has 250 mm of insulation in the walls and 300 mm in the roof, aiming for class A. But thickness only works together with the rest:
- Every window is taped round with a membrane so that moisture does not get into the frame. This has to be checked on site.
- Inside, the house is closed with a vapour barrier, outside with a wind and moisture barrier.
- An airtight house needs heat recovery ventilation: it brings in fresh air without losing heat.
Heating here is water underfloor heating from a heat pump.
06Schedule and building site
10. The schedule was counted only to the “shell”
The frame came from the factory in large sections. Three people, two on the ground and one on the crane, assembled it in about a week. Another week went on the windows. After two weeks the house looks almost finished.
The mistake is to think the build ends there. Next come insulation, membranes inside and out, the roof, the building services and the finishing. They take longer than the frame.
11. Delivery and assembly were not thought through
Large sections and panoramic windows are lifted by a truck-mounted crane. So you need access for the machinery and room for unloading. On a sloping plot this has to be checked before ordering the house kit.
12. The concrete volume was wrong
When the strip foundation was poured, more concrete was ordered than needed. The surplus was dumped on site and set in heaps.
13. The mistake was paid for twice
Now these heaps have to be broken up and carted away, the base compacted again, and only then the screed poured. A mistake in the volume turned into extra work at the next stage. Work out the concrete volume from the design and check it again before ordering.
07Where money could have been saved
This house was deliberately built without savings: it has to show the technology. To a private client I would suggest three places to save: steel supports instead of timber ones, a conventional frame where long spans are not needed, and sliding windows only where there is a way out.
08What the frame price leaves out
The most expensive mistake is to compare offers by the final figure and not look at what is behind it. The calculator shows this list next to the price. In the calculation above the manufacturer does not include:
- windows and doors;
- the foundation slab with service entries and underfloor heating;
- roof covering, gutters and roof insulation;
- painting and decoration of the facade;
- electrical and plumbing work;
- heating, heat recovery and ventilation;
- finishing of walls, floors and ceilings;
- sewerage and a well;
- the design and the building permit.
This list shows where mistakes 8, 9 and 12 come from: windows, roof insulation and the foundation are counted separately from the frame. The calculator gives quantities for them for the budget: this house has 108 m² of floor, 108 m² of ceiling and 70 m² of walls to finish.
You can calculate your own house the same way: draw the plan, place the windows and get the timber volume, wall areas and the manufacturer's price before the first call.